I.The MNH Company uses one overhead rate for the entire plant. Estimated overhead for the coming year is $450,000 and the activity level (denominator level) is estimated at 15,000 direct labor hours (DLH). Two jobs worked on this year were Job #3, which consisted of one hundred (100) plain chairs, and Job #7, which consisted of twenty (20) fancy customized chairs. Data for each job are presented below.

                               Job #3               Job #7

Direct material                $29,000         $ 1,900
Direct labor  (@$100/hr)     $ 6,000       $ 5,000

Overhead applied                 ?                  ?
The President of MNH Co. has just learned about activity-based costing (ABC) and is interested in how it might change the costs assigned to each job. After some deliberation the cost accounting group has decided that the single pool of overhead costs ($450,000) could be broken down into three smaller, more homogeneous cost pools: set-up activity, design activity, and material handling activity. The cost drivers selected for each activity are, respectively, number of set-up hours, number of design changes, and number of material loads transported. This information was presented as follows.
                               Set-up           Design           Mat.Hand

–                                  Activity          Activity          Activity

Cost                         $100,000      $300,000            $50,000

Set-up hrs                  20,000
# of design changes                       25,000
No. of loads                                                        5,000

 

                                    Job #3                   Job #7
Set-up hrs                    20                         10
Design changes           30                        400
No. of loads                   20                        5
Required
1. Under the old system (one oh rate) compute the following
a. The overhead rate
b. The overhead applied to each job
c. The total cost of each job
d. The cost per chair for each job

2. Under the new system compute
a. The overhead rates
b. The overhead applied to each job
c. The total cost of each job
d. The cost per chair for each job

3. Compare and evaluate the two systems of overhead allocation. Be as specific as possible.

 

 

II.Bill Smith worked for the ABC Company and his performance was measured against his flexible budget. He was given the following two planning budgets at the beginning of the year.
                                            10,000 units                            40,000 units

Variable production costs                    $60,000                                   $240,000

Electricity costs                                        90,000                                      330,000

Rent & insurance                                       50,000                                  50,000

Total                                                        $200,000                                    $620,000
Last month Bill’s department produced 22,000 units and incurred the following costs: Variable production costs were $140,000, electricity costs were $196,000, and the rent and insurance costs were $31,000.
Required
Evaluate Bill’s performance, supporting your conclusions quantitatively where possible.

 

III.A new company expects that for the first four months sales will be as follows.

MONTH      CASH SALES      CREDIT SALES
Jan                      $40,000          $60,000
Feb                      80,000           80,000
Mar                     130,000          300,000
Apr                     270,000          400,000
The company expects to collect credit sales in the following manner: seventy percent (70%) in the month of sale, twenty percent (20%) one month later, and the remaining ten percent (10%) two months later.
Required
Compute the expected cash collections for the month of April. SHOW ALL YOUR WORK.

How it Works

How It works ?

Step 1:- Click on Submit your Assignment here or shown in left side corner of every page and fill the quotation form with all the details. In the comment section, please mention product code mentioned in end of every Q&A Page. You can also send us your details through our email id support@assignmentconsultancy.com with product code in the email body. Product code is essential to locate your questions so please mentioned that in your email or submit your quotes form comment section.
 
Step 2:- While filling submit your quotes form please fill all details like deadline date, expected budget, topic , your comments in addition to product code . The date is asked to provide deadline.
 
Step 3:- Once we received your assignments through submit your quotes form or email, we will review the Questions and notify our price through our email id. Kindly ensure that our email id assignmentconsultancy.help@gmail.com and support@assignmentconcultancy.com must not go into your spam folders. We request you to provide your expected budget as it will help us in negotiating with our experts.
 
Step 4:- Once you agreed with our price, kindly pay by clicking on Pay Now and please ensure that while entering your credit card details for making payment, it must be done correctly and address should be your credit card billing address. You can also request for invoice to our live chat representatives.
 
Step 5:- Once we received the payment we will notify through our email and will deliver the Q&A solution through mail as per agreed upon deadline.
 
Step 6:-You can also call us in our phone no. as given in the top of the home page or chat with our customer service representatives by clicking on chat now given in the bottom right corner.
 

Features

Features for Assignment Help

Zero Plagiarism
We believe in providing no plagiarism work to the students. All are our works are unique and we provide Free Plagiarism report too on requests.

 

Relevancy
We believe in providing perfect, relevant and 100% accurate solutions to the student as per questions asked. All our experts are perfect in providing that so as to give unique experience to the students.

 

Three Stage Quality Check
We are the only service providers boasting of providing original, relevant and accurate solutions. Our three stage quality process help students to get perfect solutions.

 

 

100% Confidential
All our works are kept as confidential as we respect the integrity and privacy of our clients.

Related Services


IV.The MH Toy Company produces toy scooters that consist of one set of handlebars, a platform and two aluminum alloy wheels. In order to standardize parts the Company has designed the product so that the nuts and bolts used to attach the parts (the wheels and the handlebars) to the platform are all the same. It takes two nuts and two bolts to attach the handlebars; each wheel needs one nut and one bolt to be attached to the platform.

The Company has budgeted sales of scooters for the first six months of 2015 as follows:

Jan    12,000 units
Feb     17,000
Mar     20,000
Apr     30,000
May     6,000
June     15,000

The finished goods inventory on Dec 31, 2014 is 2,000 units. The parts inventory on 12/31/14 includes 2,500 nuts. For the year 2015 the Company has decided that each month’s finished goods ending inventory should be 20% of the next month’s demand, while the parts ending inventory should be 10% of the next two month’s demand.

Required
 
1.Prepare a production budget for scooters for the months of March, April and May (do each month separately).
2.Prepare a purchases budget for nuts for the month of March.
V .                     Standard Prime Costs per Widget
Direct material               3 lbs @ $ 25 = $ 75
Direct labor               8 hrs @ $15 = 150
Total prime costs                $275
 
The ABC Co. produced 500 widgets during the month of January, which was the first month the company was in business. The company purchased 1,700 pounds of raw material for a total price of $51,000. At month end there were 250 pounds of raw material left in inventory. The workers took 4,200 hours for the month’s production and received on average $17 .00 per hour.
 
Required
1. Compute the material price variance.
2. Compute the material quantity variance.
3. Compute the rate variance.
4. Compute the efficiency variance.
5. Compute the direct labor budget variance..
 
VI.The Singapore division of a Canadian telecommunications company uses standard costing for its machine-based production of telephone equipment. Data regarding production during June are as follows:

Variable manufacturing overhead costs incurred-$127,000
Variable manufacturing overhead cost rate&-$8 per standard machine-hour
Fixed manufacturing overhead costs incurred-$485,000
Fixed manufacturing overhead budgeted-$480,000
Denominator level in units (normal capacity)-40,000
Standard machine-hour allowed per unit of output-0.40
Units of output-42,000
Actual machine-hours used-15,800
Ending work-in process inventory-0

Required
1. Compute the variable spending and efficiency variances.
2. Compute the fixed spending and volume variances.

 

VII.Fixed overhead is budgeted at $24,000. The company actually produced 4,500 widgets in 10,000 direct labor hours. The total spending variance is $2,000 favorable; standard time per widget is set at two (2) direct labor hours. The total overhead rate is $10 per DLH. The volume variance is equal to $3,000 favorable.
 
REQUIRED
1. What was the level of actual spending?
2. How much is the efficiency variance (label it)?
3. What is the variable overhead rate?
4. What was budgeted normal capacity?
 
VIII.Hi-Speed Electronics manufactures low-cost, consumer-grade computers. It sells these computers to various electronics retailers to market under store brand names. It manufactures two computers, the Lightning 2.0 and the Lightning 2.4, which differ in terms of speed, included memory, and included hard drive capacity. The following information is available:
 
Costs per unit    Lightning 2.0    Lightning 2.4
Direct materials     $ 40    $ 75
Direct labor     100    125
Variable overhead     200 250
Fixed overhead     120    150
Total cost per unit      $460     $600
Price             $620      $900
Units sold              10,000     7,000

The average wage rate is $25 per hour. The plant has a capacity of 100,000 direct labor-hours.
 
Required
a.A nationwide discount chain has approached Hi-Speed with an offer to buy 2,000 Lightning 2.0 computers and 3,000 Lightning 2.4 computers if the price is lowered to $400 and $600, respectively, per unit. If Hi-Speed accepts the offer, how many direct labor-hours will be required to produce the additional computers? How much will the profit increase (or decrease) if Hi-Speed accepts this proposal? Prices on regular sales will remain the same.
 
b.Suppose that the customer has offered instead to buy 3,000 of L2.0 and 4,000 of L2.4 at the above special prices. How much will the profits change if the order is accepted? Assume that the company cannot increase its production capacity to meet the extra demand. (N.B. Time is the scarce resource).
IX.The M&H Co. manufactures “faces,” each one composed of one plain cookie and eight chocolate chips. Management has decided that the April ending inventory for chocolate chips should be 130,000 chips, while the beginning inventory on April 1 would be targeted at 40,000 chips. Estimated sales of “faces” for March and May are 15,500 and 18,750 units, respectively; the company desires to keep an ending inventory of “faces” equal to 20% of next month’s estimated sales. If the company has correctly projected a need to purchase 600,000 chocolate chips during the month of April, how many “faces” did the company expect to sell during April?

 

Product Code :Fin13

To get answer for this question, kindly click here (Note: Don’t forget to write the product code in comment section)

You can also email us at assignmentconsultancy.help@gmail.com but please mentioned product code in the mail body while sending emails.You can browse more questions to get answer in our Q&A sections here.

Summary