Contractor’s Cash flow
 
A developer has accepted the quotation from your company to carry out the works to lock up stage for construction of a precast concrete warehouse and Office illustrated on the attached drawing Nos. 1002, 1003A and 1004.
 
The works include demolition of an existing house and removal of a large steel framed shed:
The contract has been signed and has the following requirements:
 
Contract Price: One Million Seven Hundred and Three Thousand Dollars $ 1,703,000
Time to complete: 20 months
 
You have immediate and unrestricted access to site.
 
You are the project engineer for this job and report to the company General Manager Construction, who has control of the allowances, contingency and profit margin (i.e. 15% mark up included in the Contract Price).
 
You can read more about our case study assignment help services here.
 

How it Works

How It works ?

Step 1:- Click on Submit your Assignment here or shown in left side corner of every page and fill the quotation form with all the details. In the comment section, please mention Case Id mentioned in end of every Q&A Page. You can also send us your details through our email id support@assignmentconsultancy.com with Case Id in the email body. Case Id is essential to locate your questions so please mentioned that in your email or submit your quotes form comment section.

Step 2:- While filling submit your quotes form please fill all details like deadline date, expected budget, topic , your comments in addition to Case Id . The date is asked to provide deadline.

Step 3:- Once we received your assignments through submit your quotes form or email, we will review the Questions and notify our price through our email id. Kindly ensure that our email id assignmentconsultancy.help@gmail.com and support@assignmentconcultancy.com must not go into your spam folders. We request you to provide your expected budget as it will help us in negotiating with our experts.

Step 4:- Once you agreed with our price, kindly pay by clicking on Pay Now and please ensure that while entering your credit card details for making payment, it must be done correctly and address should be your credit card billing address. You can also request for invoice to our live chat representatives.

Step 5:- Once we received the payment we will notify through our email and will deliver the Q&A solution through mail as per agreed upon deadline.

Step 6:-You can also call us in our phone no. as given in the top of the home page or chat with our customer service representatives by clicking on chat now given in the bottom right corner.

Case Approach

Scientific Methodology

We use best scientific approach to solve case study as recommended and designed by best professors and experts in the World. The approach followed by our experts are given below:

Defining Problem

The first step in solving any case study analysis is to define its problem carefully. In order to do this step, our experts read the case two three times so as to define problem carefully and accurately. This step acts as a base and help in building the structure in next steps.

Structure Definition

The second step is to define structure to solve the case. Different cases has different requirements and so as the structure. Our experts understand this and follow student;s university guidelines to come out with best structure so that student will receive best mark for the same.

Research and Analysis

This is the most important step which actually defines the strength of any case analysis. In order to provide best case analysis, our experts not only refer case materials but also outside materials if required to come out with best analysis for the case.

Conclusion & Recommendations

A weak conclusion or recommendations spoil the entire case analysis. Our expert know this and always provide good chunks of volume for this part so that instructors will see the effort put by students in arriving at solution so as to provide best mark.

Related Services

 
The chief financial Officer of the company has issued you with the following budget for which you are to control expenditure for the project
 
Project Budget: $1,407,290 (for works excluding Prime Cost Items)

You also have to control expenditure and invoicing of Prime Cost subcontracts listed in Table 1.
 
Total Subcontractor Prime Cost payments due
$ 73,710
Debtor
Ecco Farms
(remove shed)
Demon Demos
(Demolish
House)
PowerCorp
(Power line
protection)
Local Council
(Driveway
crossover)
Payment Due Month 4 8 0 20
Amount Due -$ 2,000 $ 15,000 $ 1,500 $ 5,000
Debtor Geoff Jones Plumbing
Payment Due Month 8 12 16
Amount Due $ 4,688 $ 9,375 $ 4,688
Debtor Downtha D rain Constructions
Payment Due Month 4 8 12 16
Amount Due $ 3,546 $ 7,092 $ 10,638 $ 14,184
 
Table 1: Prime Cost Payment Schedule
 
Prime Cost (PC) expenditures are for the values and at the intervals indicated in Table 1 above. PC sums are paid by your company to the subcontractor in the month shown in Table 1. Those amounts are then claimed by your company from the Owner in the month due (Table 1) and your company receives payment one month later.
 
The expected expenditure for the project (without the PC items) follows an ‘S’ Curve (Sigmoid function) with the characteristics listed in Table 2.
 
The contractor starts work on site at date zero (month 0). At the end of the first month the amount of work completed is measured and agreed with the owner’s representative, a claim is then made for that value of work. Payment of that claim is received by the contractor at the end of the following month. This pattern of doing the work and claiming at monthly intervals continues each month until all contract works are completed. The schedule for the monthly payment claims is set out in Table
 
2. Prime Cost subcontract payments (not shown in Table 2) form part of the cashflow graph required.
 
Assignment Requirements – What You Need to Do
 
Prepare a brief (2 pages) report in Memorandum format to the Construction Manger explaining the Cash
flow expected for this project including the following information
 
1. Notification of the maximum amount of bridging finance required to cover negative expenditure
and the month at which that will occur.
2. The month in which you expect the project to commence a positive cash flow.
 
3. Contractors expenses and income as ‘S’ curves on a single graph.
4. Contractor’s Cumulative Cash flow as a graph and in an attached table.
 
You are working for a construction company and in this assignment you are required to calculate the planned cashflow for a contract. The cashflow will be used by the finance department to arrange project finance from a lender to cover the maximum expenditure. The finance manager also needs to advise the lender (bankers) when that will occur. The lender will also wish to know at what time the project will start to make a profit and how much that will be. Refer to the assignment question for details.
 